Construction Precautions for Rock Wool Cleanroom Boards

Jun 09, 2026 Leave a message

• Surface Cleaning: Clean the bonding surfaces before construction to ensure they are dust-free and oil-free.

• Waterproofing: Apply a waterproofing agent to the joints of the boards at least twice. After drying, fill with sealant, controlling the thickness to 0.5-1mm.

• Installation Sequence: Adhere the boards from bottom to top and from one corner to the other, using double-sided PE tape and structural adhesive for fixation. Remove the temporary wooden joists only after the adhesive has cured.

• Sealing: Use a special sealant at the joints in cleanrooms to ensure airtightness and prevent air leakage.

• Ventilation and Curing: Maintain ventilation during construction to ensure the adhesive fully cures and reduce VOCs release.